Microsoft Project - Hide the Resource Percentage Assignment

In Microsoft Project, when you assign a resource to a task, that resource's name is displayed to the right of the Gantt bar. But, when you assign a resource at any percentage other than 100%, you also see the assigned percentage.  You can modify the Gantt bar style to display only the resource initials without the percentage, whether it's 100% or not, by the steps below:

1.            View your Resource Sheet and type the names of each resource into the Resource Initials field

2.            View the Gantt Chart

3.            Choose Format: Bar Styles from the Menu bar

4.            Select Task

5.            Click the Text tab

6.            Click the drop-down arrow next to Resources and choose Resource Initials

Now, when you view your Gantt Chart, the entry that is listed in the Resource Initials field on the Resource Sheet is what will be displayed next to each Gantt Bar.